<?xml version="1.0"?>
<feed xmlns="http://www.w3.org/2005/Atom" xml:lang="ko">
	<id>https://en-wiki.org/index.php?action=history&amp;feed=atom&amp;title=Penal_Sum</id>
	<title>Penal Sum - 편집 역사</title>
	<link rel="self" type="application/atom+xml" href="https://en-wiki.org/index.php?action=history&amp;feed=atom&amp;title=Penal_Sum"/>
	<link rel="alternate" type="text/html" href="https://en-wiki.org/index.php?title=Penal_Sum&amp;action=history"/>
	<updated>2026-06-19T11:00:58Z</updated>
	<subtitle>이 문서의 편집 역사</subtitle>
	<generator>MediaWiki 1.33.1</generator>
	<entry>
		<id>https://en-wiki.org/index.php?title=Penal_Sum&amp;diff=743&amp;oldid=prev</id>
		<title>En-wiki: 새 문서: == 정의 == 계약서상에 명시된 지체 벌과금으로서 Delay Fine 또는 Delay Penalty라고도 한다. 이를 규정한 계약조항을 Penalty Clause라고 한다.   ==...</title>
		<link rel="alternate" type="text/html" href="https://en-wiki.org/index.php?title=Penal_Sum&amp;diff=743&amp;oldid=prev"/>
		<updated>2019-12-09T05:12:49Z</updated>

		<summary type="html">&lt;p&gt;새 문서: == 정의 == 계약서상에 명시된 지체 벌과금으로서 Delay Fine 또는 Delay Penalty라고도 한다. 이를 규정한 계약조항을 Penalty Clause라고 한다.   ==...&lt;/p&gt;
&lt;p&gt;&lt;b&gt;새 문서&lt;/b&gt;&lt;/p&gt;&lt;div&gt;== 정의 ==&lt;br /&gt;
계약서상에 명시된 지체 벌과금으로서 Delay Fine 또는 Delay Penalty라고도 한다. 이를 규정한 계약조항을 Penalty Clause라고 한다. &lt;br /&gt;
&lt;br /&gt;
== 면책 인정 ==&lt;br /&gt;
설령 공기가 지체되었다고 하더라도 아래의 경우 시공자의 면책이 인정된다.&lt;br /&gt;
* 불가항력&lt;br /&gt;
* 비상시&lt;br /&gt;
* 시공자의 통제범위를 ㅂ서어난 사유&lt;br /&gt;
* 시공자가 계약 공기내에 완공할 수 없을 정도의 새로운 작업을 지시하였을 때&lt;br /&gt;
* 시공자와 관계되지 않은 사유로 작업을 중단하였을 때&lt;br /&gt;
&lt;br /&gt;
== 지체벌과금 ==&lt;br /&gt;
지체벌과금은 통상 그 상항이 계약금액의 10%이지만 아래의 경우는 계약금액의 10%가 아니라 지체된 공사금액의 10%를 상한으로 한다.&lt;br /&gt;
* 계약공기내 비록 완공은 되지 않았더라도 발주처의 현장 사용에 지장이 없고&lt;br /&gt;
* 타 시설물의 사용에 장애를 초래하지 않으며&lt;br /&gt;
* 완공된 부분에 하자가 없을 경우&lt;br /&gt;
&lt;br /&gt;
[[Category:엔지니어링 용어사전]]&lt;/div&gt;</summary>