- 2018 임금실태조사 결과
- 2019 임금실태조사 결과
- 2019년도 엔지니어링 통계편람
- 2020 SW기술자 임금실태조사 결과
- 2020 임금실태조사 결과
- 2020년도 엔지니어링 통계편람
- 2021 건설사업관리기술인 임금실태조사 결과
- 2021 임금실태조사 결과
- 2021년도 엔지니어링 통계편람
- 2021적용 학술연구용역인건비 기준단가
- 2022 임금실태조사 결과
- 2022년도 엔지니어링 통계편람
- 2023 임금실태조사 결과
- 2023년도 엔지니어링 통계편람
- 2024 임금실태조사 결과
- 7-zip
- ASP설치에 따른 부대비용의 계상에 대하여
- Acceleration Cost
- Accent Lighting
- Acceptance Criteria
- Accepted Bidder
- Accepted Risk
- Access road
- Accommodation
- Accrued depreciation
- Actual cost
- Addition
- Additional Work
- Additive Alternate
- Adjustment
- Advance Payment
- Advanced Payment Bond
- Agency to agency arrangement
- Agent
- Agreement
- Alteration
- Alternate Bid
- Application for payment
- Article
- Artificial Obstruction
- Assessment
- Attorney in fact
- Award
- BOO
- BOT
- BTO
- BTO-a
- BTO-rs
- Base Bid
- Basic services of Architect
- Beneficial Occupancy
- Bid Evaluation
- Bid bond
- Bidding Documents
- Bidding Requirements
- Bill of Lading
- Bill of Quantities
- Bona Fide Bidder
- Bona Tide Bidder
- Bond
- Bonding Capacity
- Bonus Clause
- Builder's Risk Insurance
- Cash Allowance
- Certificate for payment
- Certificate of Occupancy
- Change Order
- Clarification
- Clarification Drawing
- Classification
- Closed Specifications
- Code of Practice
- Commencement Date
- Commissioning
- Compensation
- Completion Bond
- Completion Date
- Condemnation
- Consent of Surety
- Consortium
- Construction Budget
- Construction Cost
- Constructive Change
- Contingency Allowance
- Contract date
- Contract time
- Contracting Officer
- Contractor's Affidavit
- Contractor's Estimate
- Contractor's Option
- Contractor All Risk(CAR)
- Contructive acceleration
- Cost Reimbursement Contract
- Custom-Built
- Dwelling
- Easement
- Equipment Operation(E.O)
- Equity
- Ex-gratia
- Exposure Hazard
- Extra Work
- Extra work
- Feasibility study
- Field Order
- Field Work
- Final Acceptance
- FireFox
- Form of Tender
- Ground Cover
- Ground Floor
- Guaranted Maximum Price(GMP)
- Guarantee
- H/W 위탁 보수료의 산정방법에 대하여
- Initial Guarantee
- International Federation of Consulting Engineers(FIDIC)
- Irrevocable Credit
- Jacobs Engineering Group
- Job
- LOI
- Letter of Acceptance(L/A, LOA)
- Letter of Credit(L/C, LOC)
- Letter of Intent(LOI, L/I)
- Liquidated Damages(LD)
- Lowest Qualified Bidder
- MDB
- MOA
- MOU
- Main Contractor(MC)
- Maintenance Certificate
- Maintenance Period
- Man-Month
- Module
- Monthly Statement
- Multilateral Development Bank
- Multiple of Direct Personnel Expense
- Nominated sub-contractor(NSC)
- Non-collusion affidavit
- Non desclosure agreement
- Notice to proceed(NTP)
- Notice to tenderers
- ODA 입찰정보 사이트
- Open-End Mortgage
- Open Question
- Option Module
- Outbuilding
- PQ
- PQ(Pre-Qualification)대상 판단하기
- Partial Shipment
- Partial hand-over
- Patent defects
- Penal Sum
- Percentage Agreement
- Performance Bond
- Performance Specifications
- Permanent Work
- Potential Defects Liability
- Power of Attorney(POA)
- Pre-Qualification(PQ)
- Preamble
- Precipitable Water Vapor
- Price Fluctuation
- Prime Contractor
- Probable Construction Cost
- Progress Chart
- Progress Payment
- Project Budget
- Project Concept Pape
- Provisional Sum
- Public Liability Insurance
- Punch List
- Purchase Order
- Quantity Survey(QS)
- Quantum meruit
- Real Estate
- Record Drawing
- Reference Line
- Reimbursable Expenses
- Request For Information(RFI)
- Request For Proposal(REP)
- Residence Permit(R/P)
- Resident Engineer
- Retainage
- Retention Bond
- Retention Money
- Ribbon Develpment
- SW기술자 임금실태 조사
- Satisfaction
- Schedule of Rates
- Schematic Design
- Scope of Work
- Seal
- Selected Bidder
- Seperate Contract
- Settlement
- Shop Drawing
- Short Form Agreement
- Sight Credit
- Site Investigation
- Snagging Items
- Special Hazards Insurance
- Special Provisions
- Special Risks
- Specification
- Statement at Completion
- Statutory Bond
- Stipulated Sum Agreement
- Stop-go policy
- Streamlined Specification
- String Development
- Strip Building
- Studio Apartment
- Subcontractor
- Substantial Completion
- Successful Bidder
- Superintendent
- Superintending Officer
- Supplemental Services
- Supplementary Conditions
- Surety Bond
- Suspension
- Suspension of Work
- TOR
- Taking-over Certificate(TOC)
- Tax Abatement
- Tax Clearance Certificate
- Technical hitch
- Temporary Facility
- Temporary Hand-Over
- Temporary Work
- Tender Shoppping
- Termination Costs
- Termination of Contract
- Third Party Liability
- Time-Related Cost
- Time of Completion
- Topographic Survey
- Turn-Key Contract
- Two Envelopes System
- UL Label
- Underground Utility
- Usance Credit
- Valuable Consideration
- Value Engineering
- Variation Order
- Vehicle Detector System(VDS)
- Volume Method
- Waiver of Claim
- Wear and Tear
- Working Budget
- Working Drawing
- Workmen's Compensation Insurance
- Zoning permit
- “공사비”에 관급자재대 포함여부
- 가강수량(Precipitable Water Vapor)
- 가격엔지니어링(Cost Engineering)
- 가동중지(Shutdown)
- 가소제(Plasticizer)
- 가스 회수 시설(Gas Recovery Unit)
- 가스처리플렌트(Ethane Separation Plant)
- 가스터빈(Gas Turbine)
- 가스화(Gasification)
- 가열로(Fired Heater)
- 가이드(Guide)
- 가정기기자동화(Home Automation)
- 가정에너지 모니터링시스템(Home Energy Monitoring System)
- 가중 평균 효율(Weighted Average Conversion Efficiency)
- 가중치(Weight Value)
- 가채년수(Reserve-Production )
- 가축분뇨처리시설의 위탁운영에 대한 대가산출
- 가치공학(Value Engineering)
- 간접에너지(Indirect Energy)
- 간접인원
- 간판방식(Just In Time)
- 갈탄(Brown Coal/Lignite)
- 감가상각비(Depreciation)
- 감독(Supervision)
- 감리대가 산정시 근무일수 산정 방법에 대하여
- 감리대가 정산에 대하여
- 감압 경유(Vacuum Gas Oil)
- 감압잔사유(Vacuum Residue)
- 감압잔사유 수첨 탈황시설(Vacuum Residue Hydro Desulfurization Unit)
- 감압증류탑(Vacuum Distillation Unit)
- 강수 가능 수분량
- 개구각(Aperture Angle)
- 개발가능매장량(Exploitable Deposit)
- 개발제한구역 주민지원사업의 대가에 대하여
- 개방 전압(Open-Circuit Voltage (VOC))
- 개산계약
- 개수로(Open Channel)
- 개정(Revision)
- 개정 된 대가기준의 적용에 대하여
- 개질휘발유(Reformate)
- 건물일체형태양광발전시스템(Building Integrated Photovoltaic System)
- 건설공사의 실시설계 대가산정에 대하여
- 건설사업관리기술인 임금실태 조사
- 건성가(Dry Gas)
- 건재 일체형 태양광발전 모듈(Building Integrated Photovoltaic (Bipv) Module)
- 건축, 기계, 통신 등의 복합공정 대가계상에 대하여
- 건축 및 엔지니어링업무가 복합된 공종의 대가산출
- 건축물 구조계산서 작성업무에 대하여
- 건폐율(building coverage)
- 건화
- 걸프만협력위원회(Gulf Cooperation Council)
- 검사(Inspection)
- 견적요청(Request For Proposal)
- 결면 구조(Textured Surface)
- 경력개발제도(Career Development Program)
- 경사각(Tilt Angle)
- 경사면 일조 강도(Total (Solar) Irradiance (Gt))
- 경성탄(Hard Coal Lignite)
- 경시 변화 보정 계수(Efficiency Deviation Factor)
- 경유 수첨 탈황 시설(Gas Oil HydroDeSulfurization Unit)
- 경제협력개발기구
- 경질감압경유(Light Vacuum Gas Oil)
- 경질원유(Light Crude Oil)
- 경질중유(Bunker-A)
- 계약기간 연장에 의한 대가조정에 대하여
- 계약기간 연장으로 인한 물가조정에 대하여
- 계약변경 시 직접경비의 낙찰률 적용여부
- 계약서에 명시되지 않은 업무의 추가업무 인정여부
- 계약수행 중 기술자변경에 대하여
- 계약이행보증제도
- 계약체결방법 종류
- 계층적분석과정(Analytic Hierarchy Process)
- 계통 수전 전력량(Energy From Utility Grid)
- 계통 연계 보호 장치(Utility Interactive Protection Unit)
- 계통 연계 운전(Grid-Connected Operation, Utility Connected Operation)
- 계통 연계형 태양광발전 시스템(Grid-Connected Photovoltaic System)
- 계통도(Flow Sheet)
- 계획설계에 대한 별도 발주가능 여부에 대하여
- 고객관계관리 (Customer Relationship Management)
- 고도산화법(Advanced Oxidation Process)
- 고리형 포화탄화수소(Naphthene)
- 고립 운전(Isolated Operation)
- 고밀도폴리에틸렌(High Density Poly Ethylene)
- 고속증식로(Fast Breeding Reactor)
- 고에너지연료(High Energy Fuel)
- 고열가스 (High-Calorie Gas)
- 고온 가습-동결 시험(Humidity-Freeze Test)
- 고온 코우크스(High Temperature Coke)
- 고유황 중유(High Sulfur B-C)
- 고유황디젤유분(Light Cycle Oil)
- 고정비(Fixed Cost)
- 고정선 체결 방식(Binding Wire Type)
- 고정자 베인 작동기(Stator Vane Actuator )